General: GT11109000
Bond: 1,000,000.00
Issue Date: 11/07/11
Bid Closing Date: 28/08/11
Location:
Contracts Dept. -
Operations Division, Qatar Petroleum, PO Box 3212, Royal Plaza,G Wing,4th Floor
Rm G13,Doha
Fee: 500.00
Bond Validity: 25/01/12 -
(150) days from the Bid Closing Date
Offer Validity: 26/12/11 -
(120) days from the Bid Closing Date
Scope of Work/Description:
The scope of work
consists of the following on EPIC basis: (1) Construction and upgrade of the
existing track roads to twenty-three (23) nos. Manifolds within Dukhan Fields
to an 8m wide single carriageway asphalt road, total approximately 12,400m. (2)
,,Construction of approx 54 nos. RC road crossing culverts for approximately
eighty-three (83) pipelines / flowlines. (3) ,,Construction of underground
cable protection sleeves at all instances where electrical and
telecommunication cables cross the new roadway and for future road crossing
cables.
For more details visit Qatar Petroleum Website