CHENAB VALLEY
POWER PROJECTS PRIVATE
LIMITED (A Joint Venture of NHPC Limited, JKSPDC and PTC
India Limited) hereinafter referred to as “the Owner”, responsible to plan,
promote and organize an integrated
and efficient development
of Pakal Dul,
Kiru and Kwar hydroelectric
projects with an aggregate installed capacity of about 2120MW in the Chenab
River Basin in all its aspects in the State of Jammu & Kashmir, intends to
implement PAKAL DUL (Drangdhuran) Hydroelectric Project 1000 MW (4 x 250 MW) in
Distt. Doda, J&K, India.
The
Chenab Valley Power Projects Private Limited has invited sealed tenders
from Consortium / Companies
through International Competitive
Bidding (ICB) for Turnkey mode of execution of PAKAL DUL
(Drangdhuran) Hydroelectric
Project, 1000 MW. The scope of work shall include all
necessary additional investigations, Planning,
Design and Engineering
of all civil
structures of the project such as Coffer Dam, Concrete
Faced Rock-fill Dam, Tunnel Spillway, Surface
Spillway, Intake, Head Race Tunnel, Surge Shaft, Pressure Shaft,
Underground Power House, Tail Race Tunnel and Switchyard etc, supply of
equipment and materials, Design, Manufacturing, Supply, Installation, Testing
and Commissioning of Hydro Mechanical and Electro Mechanical Equipment /
Machinery leading to successful operation and performance of the Generating
units. After successful completion, testing and commissioning, the project is
to be handed over to CVPPPL.
Completion
Time: 72 Months
Bid
Document Fee: INR 200,000/- OR US$ 4,400/-
Sale
of Bid Documents: From 9th September 2011 to 15th September 2011
Pre
Bid Meeting: 25th October 2011, at Delhi (NCR)
Last
date of Bid submission: 15th Dec 2011, 1400 hrs
Bid
Security: INR 100,000,000/- OR US$ 2,204,000/-
Contact
Details:
General
Manager
NHPC
Officers Transit Camp
Rail
Head Complex Jammu
Tel:
+91 -191 – 2477914, Fax: +91-191-2477924
e-mail-
cvpppl@gmail.com